Construction and Reconstruction Permits

  • legal information

Under amendments to the Russian Town Planning Code introduced in 2018 by Federal Law No. 340, construction permission or carrying out reconstruction of the building was replaced by a notification procedure. The underlying purpose remained the same: before starting work, the owner must notify the relevant authorities of the intended development.

After reviewing the application, the responsible specialists either give written approval or refuse it. This document takes the form of a notification confirming that the design complies with the relevant regulations, area plan and technical requirements, taking into account the particular characteristics of a building.

Why Is Permission Required for Reconstruction or Construction?

Only an approved construction permission or reconstruction (notification confirming compliance of) authorises the commencement of works. It states:

● the applicant's full name or the development company's name;

● the reference number of the;

● the name of the building or structure;

● address;

● information from the land plot development plan;

● the date of signature and the document's validity period;

● the authorised person's signature and stamp.

Permission to Reconstruct a Building or its construction without the information listed above is invalid and may be challenged in court.

Where to Apply and Who Issues Permission

Local authorities provide this service free of charge, and the process takes up to seven working days. For a site within a historically significant settlement, the review period increases to 20 days. Approval is valid for ten years.

Depending on the complexity of the proposed construction or reconstruction, the service responsible for approving it may sit within different departments. If you are unsure, it is worth finding out in advance who issues reconstruction permission or the construction of a house, from the Main Directorate of State Construction Supervision (Gosstroynadzor).

Required Documents

The notification is accepted and its supporting documentation is reviewed within one day. Obtaining Construction Permission requires the following documents to be submitted with the notification (for reconstruction of the building the same requirements apply):

● the rights holders' consent;

● evidence of ownership;

● the architectural and urban design proposal and its approval certificate;

● the site plan;

● the design;

● the results of engineering surveys and inspections of existing structures;

● an expert assessment of the design and surveys (including is required details of the appointed company's accreditation must be provided).

A particularly common question is whether reconstruction permission is required, as the complexity of the proposed works can vary considerably. If structural alterations are planned to a house, alterations affecting the building's structural reliability and safety are made, its obtaining is required. There are a few exceptions, including non-permanent a building or house individual housing construction. The authorities also do not need to be notified when obtaining construction or reconstruction permission garages, sheds and outbuildings, provided that no commercial activity takes place on the plot.

Refusal of Construction or Reconstruction Permission

A notification submitted by an individual or a development company may be rejected. Grounds for rejection include:

● incorrectly completed the documents required for construction or reconstruction permission;

● electronic copies of insufficient quality to provide all the necessary information;

● corrections or alterations in the documents;

● use of an electronic signature that does not belong to the notifying party.

Applications are also rejected where who issues documents for review that have already expired by the application date. Before how to obtain construction permission or reconstruction, check that an equivalent notification has not already been submitted. This can happen when different departments within an organisation fail to coordinate their actions.

Refusal of permission for reconstruction or construction is generally supported by specific reasons:

● missing documents from the list required by the regulations;

● failure of the design to meet the applicable requirements;

● a proposed land use that is not permitted by law.

Once the identified issues have been resolved, a new notification may be submitted to obtain construction and reconstruction permission. An unlawful refusal may be challenged in court.

Construction or Reconstruction without Official Permission

Under Article 9.5 of the Russian Code of Administrative Offences, construction without a construction permit or notification may result in the suspension of the developer's activities and financial penalties. A decision may be made to demolish the building or bring it into compliance with the area plan, land-use rules and building regulations.

Even an unauthorised building may be legalised if it does not infringe other people's rights and meets the established safety requirements. In that situation, before obtaining how to obtain all the documents needed for lawful commissioning, it is necessary to prove in court that the building meets the criteria listed above.